Requirements

  • Permit requests should be submitted not less than five working days prior to the permit start date. 
  • A permit to work will not be granted unless a task specific risk assessment / method statement has been submitted.  The task specific risk assessment / method statement must be attached when submitting the permit request.
  • Approved permits should be collected from the permit approver (indicated in Section 6) on the day that the work commences. The approver will print and sign the permit. Permit (hard copy) to be returned to the permit approver once work is complete.
  • Asbestos information must be confirmed or acquired before proceeding with the completion of the permit request. Asbestos Information can be obtained by contacting the Asbestos manager: email: asbestosmanager@imperial.ac.uk; Tel: 020 7594 9565