Central Library improvement works

by

Rainbow paint

Redecoration and glazing works will take place at Central Library over the summer vacation.

Following the successful completion of the installation of cooling and ventilation systems at the Central Library in 2018, this summer will see the redecoration of level 1 and the entrance area. We will also be adding secondary glazing to the windows in Training Rooms 1 and 2 to reduce the noise levels in these rooms. 

There will be some minor disruption to level 1 while these works take place. 

The programme for painting is: 

  • From Monday 1 July : Training Rooms 1 and 2 
  • From Monday 8 July : outside the training rooms and the group study rooms 
  • From Thursday 18 July : Wolfson Suite 
  • From Friday 26 July : entrance and Welcome Desk / Information Hub 

Secondary glazing works will take place in August. 

For any queries please email Library Services at library@imperial.ac.uk or talk to a member of staff at the Information Hub. 

 

Reporter

Janet Corcoran

Janet Corcoran
Library Services

Click to expand or contract

Contact details

Tel: +44 (0)20 7594 8867
Email: j.m.corcoran@imperial.ac.uk

Show all stories by this author