Activity Date
Procurement – Tender process - complete January - May 2023
Discovery & Consultation - complete June to October 2023
Requirements gathering (staff and students) - complete June/July 2023
Design Phase (aligned with Imperial brand project) - complete November 2023 to April 2024
Implementation phase  March to August 2024

Priority content population

May to October 2024
Launch of new website September/October 2024

Training provided for new content types

October/November 2024
Support and Content strategy implementation November 2024 to March 2025