Project timeline
Activity | Date |
---|---|
Procurement – Tender process - Complete | Jan - May 2023 |
Discovery & Consultation - Complete | June to Oct 2023 |
Requirements gathering (Staff and students) - Complete | June / July 2023 |
Design Phase (Aligned with Imperial brand project) | Nov 2023 to April 2024 |
Implementation phase | March to Aug 2024 |
Priority content population |
May to Oct 2024 |
Launch of new website | Sept / Oct 2024 |
Training provided for new content types |
Oct / Nov 2024 |
Support and Content strategy implementation | Nov 2024 to March 2025 |